Classic cases
A certain engineering company's infringement compensation case against a certain real estate company
[Parties Involved]
Applicant for retrial (Plaintiff in the first instance, Respondent in the second instance): Shandong Certain Foundation Engineering Co., Ltd.
Authorized agent: Yang Zhi, lawyer at Shandong Shengyi Law Firm.
Respondent (Defendant in the first instance, Appellant in the second instance): Certain Real Estate Development Co., Ltd.
[Trial Result]
Revoke the second instance judgment, uphold the first instance judgment.
I. Basic Case Facts
On January 19, 2008, Certain Engineering Co., Ltd. signed a dynamic compaction construction contract with Certain Real Estate Development Co., Ltd. Under the contract, Certain Real Estate Development Co., Ltd. subcontracted the dynamic compaction work for a commercial building and a mixed-use building to Certain Engineering Co., Ltd. After the contract was signed, Certain Engineering Co., Ltd. organized personnel and equipment to enter the construction site for work. After part of the work was completed, Certain Real Estate Development Co., Ltd. believed the quality did not meet the contract standards, leading to a dispute and suspension of the contract. Subsequently, Certain Engineering Co., Ltd. repeatedly requested to remove equipment from the site but was refused and forcibly obstructed by Certain Real Estate Development Co., Ltd. On April 15, 2008, Certain Engineering Co., Ltd. filed a lawsuit requesting the return of equipment and compensation for losses. They also applied for property preservation, asking the court to take preservation measures on the equipment seized by Certain Real Estate Development Co., Ltd. The court issued ruling No. 232 to seal the equipment and its accessories. On April 25, 2008, when enforcing the ruling, Certain Real Estate Development Co., Ltd. forcibly obstructed and resisted enforcement, preventing the equipment from being removed from the site.
On September 12, 2008, the court issued civil judgment No. 232, recognizing that Certain Real Estate Development Co., Ltd.'s forcible retention of Certain Engineering Co., Ltd.'s equipment constituted an infringement of property rights, ordering the return of the seized equipment. After the judgment took legal effect, Certain Real Estate Development Co., Ltd. still did not fulfill its obligations. Certain Engineering Co., Ltd. sued again, requesting compensation for losses caused by the equipment being seized.
II. First Instance Trial Situation
(1) Claims and Defenses
Plaintiff Certain Engineering Co., Ltd. stated: The parties signed the dynamic compaction construction contract on January 19, 2008. The plaintiff worked until March 6, 2008, when the defendant changed the foundation construction plan, causing work to stop. The defendant forced the plaintiff's equipment to remain on site citing quality issues. The plaintiff filed a lawsuit to request the return of equipment and applied for preservation. A judgment has been made, but the defendant still detains the plaintiff's equipment. The defendant's illegal detention caused great losses to the plaintiff. The plaintiff requests the court to order the defendant to compensate for equipment downtime losses (from March 7, 2008, until the equipment is returned, calculated at 685.26 yuan per day) and two times of equipment removal rental, transportation, and crane fees totaling 11,000 yuan. The plaintiff reserves the right to sue again for losses on new projects caused by the defendant's illegal detention.
Defendant Certain Real Estate Development Co., Ltd. argued: 1. The defendant did not commit infringement. The equipment involved was left on site by the plaintiff to continue the dynamic compaction work. 2. The equipment's inability to operate was caused by the court's sealing. 3. The defendant applied for property preservation during arbitration but did not perform preservation due to legal restrictions on repeated seizure. However, the effects of both situations are the same. 4. The effective arbitration award is under enforcement. Based on the above, the defendant requests the court to dismiss the plaintiff's claims.
(2) Trial Result
The first instance court held: The fact that the defendant infringed on the plaintiff's property rights has been confirmed by this court's effective judgment. Because the defendant refused to execute the effective ruling and judgment, the plaintiff's equipment is still detained by the defendant on site. The plaintiff's equipment downtime fees should be compensated by the defendant. The plaintiff's expenses for renting cranes and transportation vehicles to the site, which were obstructed by the defendant causing the equipment not to be moved out, are considered extended losses. The plaintiff's request for compensation is justified and supported. The preservation ruling made by this court was for transfer sealing, not on-site detention. The defendant's claim to exempt liability based on this is contrary to facts and is not accepted.
The first instance court judgment: 1. Defendant Certain Real Estate Development Co., Ltd. shall compensate plaintiff Certain Engineering Co., Ltd. for equipment downtime depreciation fees (from April 10, 2008, until the equipment is returned, calculated at 6 shifts per day, 103.46 yuan per shift, totaling 620.76 yuan per day). 2. Defendant shall compensate plaintiff for transportation loss of 10,500 yuan.
III. Second Instance Trial Situation
(1) Claims and Defenses
Certain Real Estate Development Co., Ltd. appealed: 1. The first instance court erred in fact-finding; the plaintiff's equipment remained on site due to court seizure and detention measures. 2. The order for the appellant to compensate the appellee's losses is wrong; such losses should be borne by the appellee. 3. The first instance court's trial procedure was illegal. The appellant requests the second instance court to revoke the first instance judgment and support the appellant's claims.
Appellee Certain Engineering Co., Ltd. argued: The original court's facts were clear, laws correctly applied, and judgment correct. Requests the second instance court to uphold the first instance judgment.
(2) Trial Result
The second instance court held: The appellee filed the lawsuit on April 15, 2008, and simultaneously applied for property preservation to seal the equipment. After the first instance court approved, ruling No. 232 was issued to seal the equipment. Until the judgment on September 12, 2008, the equipment remained sealed. The rights to the equipment did not belong to either appellant or appellee during this period. Therefore, the appellee's claim for equipment downtime depreciation fees during this period lacks legal basis. Regarding the 10,500 yuan transportation fee, the second instance court agrees with the first instance court's view, omitted here.
Second instance court judgment: 1. Revoke the first instance judgment's first item. 2. Uphold the first instance judgment's second item, ordering the appellant Certain Real Estate Development Co., Ltd. to compensate appellee Certain Engineering Co., Ltd. 10,500 yuan for transportation loss within ten days of this judgment taking effect.
IV. Retrial Trial Situation
(1) Claims and Defenses
A certain engineering company, dissatisfied with the final judgment, applied to the court for a retrial, stating: On March 6, 2008, due to reasons caused by a certain real estate development company, the foundation construction plan was changed, leading to a work stoppage. The real estate development company forced the construction equipment to remain on the construction site citing engineering quality issues. The engineering company repeatedly requested to withdraw the equipment from the site but was refused and forcibly obstructed. In response, the engineering company reported to the public security authorities on April 10, 2008. On April 25, 2008, during the enforcement of the ruling, the real estate development company organized personnel to forcibly obstruct and resist enforcement, causing the construction equipment to fail to be moved out of the site. The actions of the real estate development company were violations, and the direct consequence was the direct loss to the engineering company. In this case, Civil Ruling No. 232 ordered the sealing of the dynamic compaction construction equipment and ancillary facilities involved in the case, which does not affect the property rights of the owner of the equipment. It is requested to revoke the second-instance judgment and uphold the first-instance judgment. The real estate company should compensate the engineering company for the equipment's depreciation during operation.
(2) Trial Result
The retrial court held that: Before the lawsuit on April 10, 2008, the engineering company requested the real estate company to return the equipment, claiming the equipment was detained by the real estate company. The "Police Incident Registration Form" confirmed the dispute between the parties. On April 15, 2008, the engineering company filed a lawsuit demanding the return of the equipment and requested the court to take preservation measures on the equipment detained by the real estate company. On the same day, the court issued Civil Ruling No. 232, ordering the sealing of the dynamic compaction construction equipment and ancillary facilities involved in the case. Although the equipment was sealed, the rights to the equipment still belonged to the engineering company. Moreover, the preservation measures were based on the real estate company's detention of the equipment, and the engineering company was not at fault. On April 25, 2008, when the engineering company applied for enforcement of the ruling, the real estate company organized personnel to forcibly obstruct and resist enforcement, causing the construction equipment to fail to be moved out of the site. The real estate company's actions were at fault. After the effective Civil Judgment No. 232 issued on September 12, 2008, the real estate company still did not return the equipment.
In this case, the engineering company filed a lawsuit on September 25, 2008, demanding the real estate company compensate for losses. The fact that the real estate company infringed on property rights was confirmed by the effective judgment. The appraisal report by Shandong Engineering Consulting Company identified losses due to equipment stagnation. Because the real estate company resisted enforcement, the equipment was detained by the real estate company and returned on September 10, 2009. Therefore, the original first-instance judgment that the real estate company should compensate the engineering company for the equipment's depreciation during operation was appropriate. The engineering company's application for retrial is justified and should be supported by this court. The original second-instance judgment was incorrect in fact-finding and legal application and is hereby corrected by this court.
The retrial court's judgment: 1. Revoke the second-instance judgment. 2. Uphold the first-instance judgment.
5. Lawyer's Analysis
After the first-instance judgment in this case, the second-instance judgment was reversed, and later the first-instance judgment was upheld again through retrial. It was truly a rollercoaster, and the efforts made by the lawyers during this period are self-evident.
The dispute in this case focuses on who should bear the equipment depreciation costs during operation, that is, the issue of who should bear the losses suffered by the preserved property during the property preservation period due to inability to operate normally. According to the principle of "fault liability," to clarify this issue, it is necessary to first determine whose fault caused the loss. On the surface, it seems that the court's preservation measures caused the equipment stagnation, but ultimately, the preservation measures were based on the real estate company's detention of the equipment, and the engineering company was not at fault throughout the process. Therefore, the real estate company should bear the compensation responsibility.
The principles of liability in civil law include the fault liability principle (including the presumption of fault liability), no-fault liability principle, and equitable liability principle. During the property preservation period, if the sealing, detention, or freezing of the respondent's property affects the respondent's normal production and operation activities causing certain losses, the compensation issue should be handled according to the "fault liability" principle. This principle is reflected in the relevant provisions of the Civil Procedure Law of the People's Republic of China. Articles 92 and 93 of the Civil Procedure Law stipulate that the people's court has the right to require the applicant to provide a guarantee when taking property preservation measures. The purpose is to ensure that if the property preservation application is erroneous, the respondent's property losses can be compensated in a timely manner. If the case result is unfavorable to the applicant and the property preservation application is erroneous, the applicant should compensate for the loss. Conversely, if the application is not erroneous, the respondent should bear the loss, i.e., "whoever is at fault compensates."
Of course, in general cases, preservation measures mostly target the respondent's property. In this case, due to the special nature of the performance subject, the preservation measures targeted the applicant's property, but the principle of liability remains the "fault liability" principle. This case was caused by the real estate company's fault in detaining the machinery and equipment, which led to the preservation measures. Therefore, the real estate company should bear the depreciation costs of the machinery and equipment during the preservation period.