Adjustment of Construction Project Duration and Costs During the COVID-19 Pandemic Prevention and Control Period
The novel coronavirus pneumonia epidemic has spread nationwide. The construction industry has been greatly affected by the epidemic. Construction projects under construction nationwide were basically in a state of suspension during the COVID-19 pandemic.
Legal risk prevention related to construction project contracts caused by the COVID-19 pandemic, risk bearing during contract performance, and how to reasonably share issues such as delays, costs, and losses caused by the epidemic with the employer urgently need to be resolved. Only by safeguarding the legitimate rights and interests of the contractor can the smooth implementation of the project be ensured.
1. The contractor of the construction project contract can claim exemption from related contractual responsibilities by asserting that the epidemic is a force majeure event that prevents contract performance.
On February 10, the Legislative Affairs Commission of the Standing Committee of the National People's Congress answered legal questions widely concerned by society during epidemic prevention and control. Regarding enterprises' feedback that many contractual obligations cannot be normally performed due to the epidemic, Zang Tiewei, spokesperson and director of the research office of the Legislative Affairs Commission, said that the outbreak of the novel coronavirus pneumonia epidemic is a sudden public health event in China. To protect public health, the government has taken corresponding epidemic prevention and control measures. For parties unable to perform contracts due to this, it constitutes force majeure that is unforeseeable, unavoidable, and insurmountable. According to relevant provisions of the Contract Law, parties unable to perform contracts due to force majeure may be partially or fully exempted from liability depending on the impact of the force majeure, except where otherwise provided by law.
2. Regarding adjustment of construction periods.
Article 17.1 of the General Terms in the "Construction Project Contract (Model Text)" (GF—2017—0201) stipulates that after the occurrence of force majeure, the employer and contractor should collect evidence proving the occurrence of force majeure and the losses caused by it, and promptly and carefully calculate the losses incurred.
Article 17.3.2(4) of the General Terms stipulates: If the contractor's performance of contractual obligations is affected by force majeure causing or likely to cause a delay in the construction period, the construction period shall be extended accordingly. The costs and losses caused by the contractor's suspension of work shall be reasonably shared by the employer and the contractor, and wages for workers during the suspension period must be borne by the employer.
According to Article 117, Paragraph 1 of the Contract Law, "If a contract cannot be performed due to force majeure, liability shall be partially or fully exempted according to the impact of the force majeure...", the contractor may also apply to the employer for an extension of the construction period and be exempted from liability for delay.
Shandong Provincial Department of Housing and Urban-Rural Development's "Notice on Matters Related to Construction Project Pricing During the Prevention and Control of the Novel Coronavirus Pneumonia Epidemic" regarding construction period adjustments:
Affected by the COVID-19 epidemic, the construction period should be extended in accordance with Article 9.10 on force majeure in the "Standard for Bill of Quantities and Pricing of Construction Projects" (GB50500-2013). For projects that have not resumed work during the epidemic prevention and control period, the extension generally starts from the date the project receives the suspension notice from the local management department until the date the resumption permit is received; for projects that have resumed work during the epidemic prevention and control period, the extension shall be determined through negotiation between the employer and contractor based on the actual situation. The normal Spring Festival holiday already considered in the contract period shall not be included in the extension.
3. Regarding cost adjustments.
Shandong Provincial Department of Housing and Urban-Rural Development's "Notice on Matters Related to Construction Project Pricing During the Prevention and Control of the Novel Coronavirus Pneumonia Epidemic" stipulates:
Costs incurred due to suspension of construction for epidemic prevention in ongoing projects shall be reasonably shared by the employer and contractor according to laws, regulations, contract terms, and Article 9.11 on force majeure in the "Standard for Bill of Quantities and Pricing of Construction Projects" (GB50500-2013).
For projects that resume work during the epidemic prevention and control period, epidemic prevention measures must be strictly implemented to ensure personnel safety and prevent epidemic spread. Cost changes caused thereby shall be negotiated and adjusted by the employer and contractor based on contract provisions and the following regulations, adhering to the principles of seeking truth from facts and sharing risks.
During the epidemic prevention and control period, epidemic prevention fees are added. These fees refer to costs for masks, alcohol, disinfectants, gloves, thermometers, electric sprayers, and other epidemic protection materials required during construction, protective labor costs, efficiency losses caused by protection, and other expenses incurred from implementing protective measures. These are calculated based on the number of construction and management personnel at the site, at a standard of 40 yuan per person per day, and included in a special epidemic prevention fund. This fee only participates in the calculation of construction industry VAT. Construction units must prioritize the life safety and health of frontline workers and make full use of the epidemic prevention fund for its designated purpose.
During the epidemic prevention and control period, changes in labor and material prices shall be adjusted according to the "Opinions of the Shandong Provincial Department of Housing and Urban-Rural Development on Strengthening Risk Control of Labor and Material Prices in Construction Projects" (Lu Jian Biao Zi [2019] No. 21). If the contract stipulates no adjustment, the principle of changed circumstances applies during the epidemic prevention period, and risks shall be reasonably shared according to the above document.
For projects required to resume work during the epidemic prevention period or after the lifting of epidemic prevention, if expedited work is needed, the expedited costs should be calculated separately after expert evaluation.
However, after the occurrence of force majeure, both parties to the contract should take measures to avoid and reduce the expansion of losses as much as possible. Any party that fails to take effective measures leading to expanded losses shall be liable for the expanded losses.
If one party delays performance of contractual obligations and encounters force majeure during the delay, this does not exempt them from liability for breach of contract.
Construction, epidemic, force majeure, construction period, duration, project, cost, contract, contractor
Recommended lawyer
Immediate consultation to provide you with legal services
Your information has been encrypted and protected, please feel free to fill it in
Shandong Shengyi Law Firm
Phone: +86-53188070707
Website: www.sdsyls.cn
Email: shengyilvshi@163.com
Address: 42nd Floor, Building 4, Lushang Guo'ao City, No. 9777 Jingshi Road, Lixia District, Jinan City, Shandong Province, East of Provincial High Court
WeChat Official Account
COOKIES
Our website uses cookies and similar technologies to personalize the advertising shown to you and to help you get the best experience on our website. For more information, see our Privacy & Cookie Policy
COOKIES
Our website uses cookies and similar technologies to personalize the advertising shown to you and to help you get the best experience on our website. For more information, see our Privacy & Cookie Policy
These cookies are necessary for basic functions such as payment. Standard cookies cannot be turned off and do not store any of your information.
These cookies collect information, such as how many people are using our site or which pages are popular, to help us improve the customer experience. Turning these cookies off will mean we can't collect information to improve your experience.
These cookies enable the website to provide enhanced functionality and personalization. They may be set by us or by third-party providers whose services we have added to our pages. If you do not allow these cookies, some or all of these services may not function properly.
These cookies help us understand what you are interested in so that we can show you relevant advertising on other websites. Turning these cookies off will mean we are unable to show you any personalized advertising.