Supreme People's Court Provisions on Several Issues Concerning the Trial of Foreign-Invested Enterprise Dispute Cases (I)
Supreme People's Court Provisions on Several Issues Concerning the Trial of Disputes in Foreign-Invested Enterprises (I) ( Adopted at the 1487th meeting of the Judicial Committee of the Supreme People's Court on May 17, 2010, amended according to the "Decision of the Supreme People's Court on Amending Twenty-nine Commercial Judicial Interpretations Including the Reply of the Supreme People's Court on Whether the State-Allocated Land Use Rights of Bankrupt Enterprises Should be Included in Bankruptcy Property" passed at the 1823rd meeting of the Judicial Committee of the Supreme People's Court on December 23, 2020) 。
To properly try disputes arising during the establishment, alteration, and other processes of foreign-invested enterprises and to protect the legitimate rights and interests of the parties, these provisions are formulated in accordance with the Civil Code of the People's Republic of China, the Foreign Investment Law of the People's Republic of China, the Company Law of the People's Republic of China, and other laws and regulations, combined with judicial practice.
Article 1 Contracts concluded by the parties during the establishment, alteration, and other processes of foreign-invested enterprises that require approval by the foreign-invested enterprise approval authority according to laws and administrative regulations shall take effect from the date of approval; if not approved, the people's court shall recognize that the contract has not taken effect. If a party requests the court to declare the contract invalid, the court shall not support it.
The invalidity of the contract due to lack of approval as mentioned in the preceding paragraph does not affect the validity of the clauses obliging the parties to fulfill approval obligations and related clauses established because of such obligations.
Article 2 If the supplementary agreement reached by the parties on matters related to foreign-invested enterprises does not constitute a major or substantial change to the approved contract, the people's court shall not recognize the supplementary agreement as ineffective on the grounds that it was not approved by the foreign-invested enterprise approval authority.
Major or substantial changes as stipulated in the preceding paragraph include changes in registered capital, company type, business scope, business term, shareholders' subscribed capital contribution amount, contribution method, as well as company mergers, company splits, and equity transfers.
Article 3 If the people's court finds that a foreign-invested enterprise contract approved by the foreign-invested enterprise approval authority has invalid circumstances prescribed by laws or administrative regulations during the trial, it shall declare the contract invalid; if the contract has revocable circumstances prescribed by laws or administrative regulations and a party requests revocation, the people's court shall support it.
Article 4 If a foreign-invested enterprise contract stipulates that one party shall contribute or provide cooperation conditions with subject matter requiring ownership change registration, and the subject matter has been delivered for actual use by the foreign-invested enterprise, and the party obligated to complete the ownership change registration has done so within a reasonable period designated by the people's court, the court shall recognize that the party has fulfilled the obligation to contribute or provide cooperation conditions. If the foreign-invested enterprise or its shareholders claim that the party does not enjoy shareholder rights on the grounds of failure to fulfill the contribution obligation, the people's court shall not support it.
If the foreign-invested enterprise or its shareholders provide evidence proving that the party caused losses to the foreign-invested enterprise due to delayed ownership change registration and request compensation, the people's court shall support it.
Article 5 After the establishment of a foreign-invested enterprise equity transfer contract, if the transferor and the foreign-invested enterprise fail to fulfill the approval obligations, and after the transferee's reminder, still fail to do so within a reasonable period, and the transferee requests contract termination and the return of the transfer payment already made by the transferor, as well as compensation for actual losses caused by failure to fulfill approval obligations, the people's court shall support it.
Article 6 After the establishment of a foreign-invested enterprise equity transfer contract, if the transferor and the foreign-invested enterprise fail to fulfill the approval obligations, and the transferee files a lawsuit with the transferor as defendant and the foreign-invested enterprise as a third party, requesting that the transferor and the foreign-invested enterprise jointly fulfill the approval obligations within a certain period, the people's court shall support it. If the transferee also requests to perform the approval themselves if the transferor and the foreign-invested enterprise fail to fulfill the approval obligations within the period determined by the effective judgment, the people's court shall support it.
If the transferor and the foreign-invested enterprise refuse to fulfill the approval obligations within the period determined by the effective judgment of the people's court, and the transferee files another lawsuit requesting contract termination and compensation for losses, the people's court shall support it. The scope of compensation may include the price difference loss of equity, equity income, and other reasonable losses.
Article 7 If the transferor, foreign-invested enterprise, or transferee fails to obtain approval from the foreign-invested enterprise approval authority for the equity transfer contract approval as stipulated in the first paragraph of Article 6 of these provisions, and the transferee files another lawsuit requesting the transferor to return the transfer payment already made, the people's court shall support it. If the transferee requests the transferor to compensate for the resulting losses, the people's court shall determine whether the transferor shall bear compensation liability and the specific amount based on whether the transferor is at fault and the degree of fault.
Article 8 If the foreign-invested enterprise equity transfer contract stipulates that the transferor shall handle approval procedures only after the transferee pays the transfer payment, and the transferee fails to pay the equity transfer payment, and after the transferor's reminder, still fails to do so within a reasonable period, and the transferor requests contract termination and compensation for actual losses caused by delayed performance, the people's court shall support it.
Article 9 After the establishment of a foreign-invested enterprise equity transfer contract, if the transferee fails to pay the equity transfer payment, and the transferor and the foreign-invested enterprise also fail to fulfill the approval obligations, and the transferor requests the transferee to pay the equity transfer payment, the people's court shall suspend the trial and order the transferor to handle the approval procedures within a certain period. If the equity transfer contract obtains approval from the foreign-invested enterprise approval authority, the people's court shall support the transferor's litigation request for payment of the transfer payment.
Article 10 After the establishment of a foreign-invested enterprise equity transfer contract, if the transferee has actually participated in the operation and management of the foreign-invested enterprise and obtained income, but the contract has not been approved by the foreign-invested enterprise approval authority, and the transferor requests the transferee to withdraw from the operation and management of the foreign-invested enterprise and pay the income obtained from actual participation in operation and management to the transferor after deducting related costs and expenses, the people's court shall support it.
Article 11 If a shareholder of a foreign-invested enterprise transfers all or part of the equity to a third party outside the shareholders, it shall be unanimously agreed by the other shareholders. If the other shareholders request the cancellation of the equity transfer contract on the grounds that their consent was not obtained, the people's court shall support it. The following circumstances are exceptions:
(1) There is evidence proving that the other shareholders have already agreed;
(2) The transferor has given written notice of the equity transfer matter, and the other shareholders have not responded within thirty days from the date of receipt of the written notice;
(3) The other shareholders disagree with the transfer but do not purchase the transferred equity.
Article 12 If a shareholder of a foreign-invested enterprise transfers all or part of the equity to a third party outside the shareholders, and the other shareholders request the cancellation of the equity transfer contract on the grounds that the equity transfer infringes their preemptive purchase rights, the people's court shall support it. Except where the other shareholders have not asserted their preemptive purchase rights within one year from the date they knew or should have known of the signing of the equity transfer contract.
If the transferor or transferee in the preceding paragraph requests the court to declare the equity transfer contract invalid on the grounds of infringing other shareholders' preemptive rights, the people's court shall not support it.
Article 13: The equity pledge contract concluded between shareholders of foreign-invested enterprises and creditors shall take effect upon establishment, unless otherwise stipulated by laws, administrative regulations, or the contract. Failure to register the pledge does not affect the validity of the equity pledge contract.
If a party claims the equity pledge contract is invalid or ineffective solely because it has not been approved by the foreign-invested enterprise's approval authority, the people's court shall not support it.
If the equity pledge contract has been registered in accordance with the relevant provisions of the Civil Code, the equity pledge shall be established upon registration.
Article 14: If the parties agree that one party makes the actual investment and the other acts as the nominal shareholder of the foreign-invested enterprise, the people's court shall not support the actual investor's request to confirm their shareholder status or to change the shareholders of the foreign-invested enterprise, except under the following conditions:
(1) The actual investor has made the actual investment;
(2) Other shareholders besides the nominal shareholder recognize the actual investor's shareholder status;
(3) The people's court or the parties have obtained the consent of the foreign-invested enterprise's approval authority during litigation to change the actual investor to a shareholder.
Article 15: If a contract stipulates that one party makes the actual investment and the other acts as the nominal shareholder of the foreign-invested enterprise, and there are no invalid circumstances prescribed by laws or administrative regulations, the people's court shall recognize the contract as valid. If a party claims the contract is invalid or ineffective solely because it has not been approved by the foreign-invested enterprise's approval authority, the people's court shall not support it.
If the actual investor requests the nominal shareholder of the foreign-invested enterprise to perform corresponding obligations according to their agreement, the people's court shall support it.
If the parties have not agreed on profit distribution, and the actual investor requests the nominal shareholder of the foreign-invested enterprise to deliver the income obtained from the foreign-invested enterprise, the people's court shall support it. If the nominal shareholder requests necessary remuneration from the actual investor, the people's court shall support it at its discretion.
Article 16: If the nominal shareholder of the foreign-invested enterprise fails to perform the contract with the actual investor, causing the actual investor to be unable to achieve the contract's purpose, and the actual investor requests to terminate the contract and hold the nominal shareholder liable for breach of contract, the people's court shall support it.
Article 17: If the actual investor directly requests profit distribution or exercises other shareholder rights from the foreign-invested enterprise according to the agreement with the nominal shareholder, the people's court shall not support it.
Article 18: If the contract between the actual investor and the nominal shareholder of the foreign-invested enterprise is declared invalid, and the value of the equity held by the nominal shareholder is higher than the actual investment amount, the actual investor requests the nominal shareholder to return the investment and reasonably distribute the equity income between the parties based on the actual investment and the nominal shareholder's participation in the enterprise's management, the people's court shall support it.
If the nominal shareholder of the foreign-invested enterprise explicitly waives or refuses to continue holding the equity, the people's court may order the proceeds from auctioning or selling the nominal shareholder's equity to be returned to the actual investor, with the remaining funds reasonably distributed between the parties based on the actual investment and the nominal shareholder's participation in management.
Article 19: If the contract between the actual investor and the nominal shareholder of the foreign-invested enterprise is declared invalid, and the value of the equity held by the nominal shareholder is lower than the actual investment amount, the actual investor requests the nominal shareholder to return the equivalent value of the existing equity, the people's court shall support it; if the nominal shareholder explicitly waives or refuses to continue holding the equity, the people's court may order the proceeds from auctioning or selling the nominal shareholder's equity to be returned to the actual investor.
If the actual investor requests compensation for losses from the nominal shareholder, the people's court shall determine whether the nominal shareholder bears compensation liability and the amount based on whether the nominal shareholder is at fault for the contract's invalidity and the degree of fault.
Article 20: If the contract between the actual investor and the nominal shareholder of the foreign-invested enterprise is declared invalid due to malicious collusion that harms the interests of the state, collective, or third parties, the people's court shall confiscate the property obtained thereby to the state or return it to the collective or third parties.
Article 21: If a shareholder of a foreign-invested enterprise or the enterprise itself applies to the approval authority for changing the shareholders listed in the approval certificate by providing false materials, fraud, or other improper means, causing other shareholders to lose their shareholder status or original equity shares, and the other shareholders request confirmation of their shareholder status or original equity shares, the people's court shall support it, except where a third party has acquired the equity in good faith.
If the other shareholders request the infringing shareholder or the foreign-invested enterprise to compensate for losses, the people's court shall support it.
Article 22: The people's court shall apply these provisions by reference when hearing disputes arising from investments made by investors from the Hong Kong Special Administrative Region, Macau Special Administrative Region, Taiwan region, or Chinese citizens residing abroad in establishing enterprises in the mainland.
Article 23: After the implementation of these provisions, cases still in the first or second instance shall apply these provisions; cases that have been finally adjudicated before the implementation shall not apply these provisions upon retrial by the people's court.
Article 24: If any previous judicial interpretations made by this court conflict with these provisions before their implementation, these provisions shall prevail.
Supreme People's Court, foreign-invested enterprises, shareholders, transfer, people's court, equity, contract, actual, request, support