News and updates
Supreme People's Court Interpretation on the Application of Law in Cases Involving Disputes over State-owned Land Use Rights Contracts
Interpretation of the Supreme People's Court on the Application of Law in Trials of Disputes Involving State-owned Land Use Rights Contracts ( Adopted at the 1334th meeting of the Judicial Committee of the Supreme People's Court on November 23, 2004, amended according to the Decision of the Supreme People's Court on Amending Twenty-seven Civil Judicial Interpretations Including the Interpretation on the Application of the Trade Union Law of the People's Republic of China in Civil Trials, passed at the 1823rd meeting of the Judicial Committee of the Supreme People's Court on December 23, 2020) 。
To properly try disputes involving state-owned land use rights contracts and legally protect the legitimate rights and interests of the parties, this interpretation is formulated in accordance with the Civil Code of the People's Republic of China, the Land Administration Law of the People's Republic of China, the Urban Real Estate Administration Law of the People's Republic of China, and other laws, combined with civil trial practice.
I. Disputes over Land Use Rights Grant Contracts
Article 1 The land use rights grant contract referred to in this interpretation means a contract in which the natural resources authority of the municipal or county people's government, as the grantor, grants the state-owned land use rights to the grantee for a certain period, and the grantee pays the land use rights grant fee.
Article 2 A land use rights grant contract concluded between the Development Zone Management Committee as the grantor and the grantee shall be deemed invalid.
Before the implementation of this interpretation, if the Development Zone Management Committee concluded a land use rights grant contract as the grantor with the grantee, and the contract was ratified by the natural resources authority of the municipal or county people's government before litigation, the contract may be deemed valid.
Article 3 If the land use rights are granted by agreement with the approval of the municipal or county people's government, and the land use rights grant fee is lower than the minimum price set by the local government according to national regulations at the time of contract conclusion, the price clause in the land use rights grant contract shall be deemed invalid.
If a party requests to pay the land use rights grant fee according to the market appraisal price at the time of contract conclusion, such request shall be supported; if the grantee refuses to make up the difference according to the market appraisal price and requests contract termination, such request shall be supported. Losses caused thereby shall be borne by the parties according to fault.
Article 4 If the grantor of the land use rights grant contract cannot deliver the land due to failure to complete the approval procedures for the land use rights grant, and the grantee requests contract termination, such request shall be supported.
Article 5 If the grantee, with the consent of the grantor and the urban planning administrative department of the municipal or county people's government, changes the land use stipulated in the land use rights grant contract, and a party requests adjustment of the land use rights grant fee according to the standard for land of the same use at the time of litigation, such request shall be supported.
Article 6 If the grantee changes the land use stipulated in the land use rights grant contract without authorization, and the grantor requests contract termination, such request shall be supported.
II. Disputes over Land Use Rights Transfer Contracts
Article 7 The land use rights transfer contract referred to in this interpretation means a contract in which the land use rights holder, as the transferor, transfers the granted land use rights to the transferee, who pays the price.
Article 8 After the land use rights holder, as the transferor, concludes a land use rights transfer contract with the transferee, a party's request to declare the contract invalid on the grounds that the land use rights change registration procedures between the parties have not been completed shall not be supported.
Article 9 If the land use rights holder, as the transferor, concludes several transfer contracts for the same granted land use rights, and the transfer contracts are valid, and the transferees all request contract performance, the following situations shall be handled separately:
(1) If the transferee has completed the land use rights change registration procedures, the request for the transferor to perform obligations such as land delivery shall be supported;
(2) If none have completed the land use rights change registration procedures, but a transferee has lawfully occupied and developed the land, the request for the transferor to perform obligations such as land use rights change registration shall be supported;
(3) If none have completed the land use rights change registration procedures and none have lawfully occupied and developed the land, the transferee who paid the land transfer price first requests the transferor to perform obligations such as land delivery and land use rights change registration, such request shall be supported;
(4) If none of the contracts have been performed, the transferee of the contract established earlier according to law requests contract performance, such request shall be supported.
If a transferee who has not obtained the land use rights requests contract termination and compensation for losses, it shall be handled in accordance with relevant provisions of the Civil Code.
Article 10 If the land use rights holder and the transferee conclude a contract to transfer allocated land use rights, and before litigation the transfer is approved by the competent people's government and the transferee completes the land use rights grant procedures, the contract between the land use rights holder and the transferee may be treated as a compensation contract.
Article 11 If the land use rights holder and the transferee conclude a contract to transfer allocated land use rights, and before litigation the competent people's government decides not to handle the land use rights grant procedures and directly allocates the land use rights to the transferee, the contract between the land use rights holder and the transferee may be treated as a compensation contract.
III. Disputes over Cooperative Real Estate Development Contracts
Article 12 The cooperative real estate development contract referred to in this interpretation means a contract in which the parties agree to jointly invest by providing granted land use rights, funds, etc., sharing profits and risks, to cooperatively develop real estate.
Article 13 If one party to the cooperative real estate development contract has real estate development and operation qualifications, the contract shall be deemed valid.
If neither party has real estate development and operation qualifications, the contract shall be deemed invalid. However, if before litigation one party has obtained such qualifications or has lawfully cooperated to establish a real estate development enterprise with such qualifications, the contract shall be deemed valid.
Article 14 If the investment amount exceeds the agreed amount in the cooperative real estate development contract, and the parties cannot agree on the proportion of bearing the increased investment, it shall be determined according to the party's breach of contract; if the cause is not attributable to the parties or the breach situation cannot be determined, it shall be determined according to the agreed investment ratio; if no investment ratio is agreed, it shall be determined according to the agreed profit distribution ratio.
Article 15 If the actual building area of the house is less than the agreed amount in the cooperative real estate development contract, and the parties cannot agree on the distribution ratio of the actual building area, it shall be determined according to the party's breach of contract; if the cause is not attributable to the parties or the breach situation cannot be determined, it shall be determined according to the agreed profit distribution ratio.
Article 16 In the following circumstances, a party to the cooperative real estate development contract requesting distribution of real estate project benefits shall not be accepted; if already accepted, the lawsuit shall be dismissed:
(1) Real estate construction projects requiring approval have not been approved by the competent people's government department with approval authority;
(2) Real estate construction projects have not obtained construction project planning permits;
(3) Unauthorized changes to construction project planning.
Losses caused by a party concealing the fact of changes in construction project planning shall be borne by the party at fault.
Article 17: If the actual building area of a house exceeds the planned building area, and is approved by the competent government authority with approval power, if the parties fail to agree on the allocation ratio of the excess part of the house, the profit distribution ratio agreed upon shall be used. If the parties fail to agree on the proportion of the increased investment amount, the agreed investment ratio shall be used; if no investment ratio is agreed upon, the agreed profit distribution ratio shall be used.
Article 18: If a party violates the planning and development of a house and it is identified as an illegal building by the competent government authority with approval power and ordered to be demolished, if the parties fail to agree on the loss responsibility, the responsibility shall be determined according to the party's fault; if the fault cannot be determined, the responsibility shall be determined according to the agreed investment ratio; if no investment ratio is agreed upon, the responsibility shall be determined according to the agreed profit distribution ratio.
Article 19: If the cooperative real estate development contract stipulates that the profit distribution ratio is determined only by the investment amount, and the party fails to pay the full capital contribution, the profit shall be distributed according to the party's actual investment ratio.
Article 20: If a party to a cooperative real estate development contract requests to offset the house pre-sale payment against the investment to participate in profit distribution, it shall not be supported.
Article 21: If a party to a cooperative real estate development contract who provides land use rights does not bear business risks and only receives fixed benefits, it shall be recognized as a land use rights transfer contract.
Article 22: If a party to a cooperative real estate development contract who provides funds does not bear business risks and only receives a fixed number of houses, it shall be recognized as a house sale contract.
Article 23: If a party to a cooperative real estate development contract who provides funds does not bear business risks and only receives a fixed amount of money, it shall be recognized as a loan contract.
Article 24: If a party to a cooperative real estate development contract who provides funds does not bear business risks and only uses the house in the form of leasing or other forms, it shall be recognized as a house lease contract.
4. Others
Article 25: This interpretation shall come into effect from August 1, 2005; the first-instance cases accepted after the implementation shall apply this interpretation.
If the judicial interpretations issued by the Supreme People's Court before the implementation of this interpretation are inconsistent with this interpretation, this interpretation shall prevail.
Supreme People's Court, land, contract, right of use, parties, transferee, transfer, according to, agreement, real estate
Recommended lawyer